| Asset type | Social infrastructure |
| Status | Operational |
| Asset Description | 92.5% interest in two portfolios (Aster and Bloom) comprising of 26 facilities representing 4,114 beds located in Alberta and B.C. AgeCare is the operator and owns the balance of the equity ownership interests in the two portfolios. |
| Asset Revenues | Long-term care facilities are licensed, regulated and funded by the provincial government. The provincial government subsidizes the care, programs, supplies and accommodation costs of the residents, who are also subject to a co-payment. The funding rates paid by the government and the residents to the operators are set on an annual basis. |
| Counterparty | Alberta Health Services (agency of the provincial government), Various B.C. Regional Health Authorities (agencies of the provincial government) |
| Asset Type | Energy Infrastructure |
| Status | Operational (COD between November 2014 and January 2015) |
| Asset Description | Three solar PV facilities with 41 MWdc of aggregate generation capacity. Projects were developed by Canadian Solar Solutions Inc. under the Ontario government’s FIT program. |
| Asset Revenues | 100% of power produced is sold under 20-year Power Purchase Agreements (PPAs) |
| Counterparty | IESO |
| PPA Expiry | 2034 for 2 assets and 2035 for the other (20 years following COD) |
| Asset Type | Energy Infrastructure |
| Status | Operational (construction completed in December 2014) |
| Project Description | 101.2 MW wind farm located in the Québec municipalities of Ste-Marguerite-Marie and Causapscal which was developed by Axium Infrastructure under Hydro-Québec’s 2005 call for power. |
| Asset Revenues | 100% of power produced is sold under a 20-year Power Purchase Agreement (PPA) |
| Counterparty | Hydro-Québec |
| PPA expiry | December 2034 (20 years following COD) |
| Asset Type | Social Infrastructure (Student Housing) |
| Status | Under Construction (Commercial Operations in 2023) |
| Asset Description | Mass Ave Housing Partners is a concession from the University of Massachusetts Amherst to construct and operate on-campus undergraduate and graduate student housing facility . The undergraduate facility will feature 253 apartments with a total of 623 beds and the graduate facility will feature 140 apartments with a total of 201 beds. Construction of the undergraduate and graduate facilities is expected to be completed by the ends of August 2023 and November 2023, respectively. The facility will be operated pursuant to a concession agreement with the University for a 65-year term. The Project Company has the authority to set rental rate and operating budgets, and will retain a third-party property manager responsible for maintenance of the property as well as unit leasing and rent collection. |
| Asset Revenues | Rental revenue is collected from students every month. Approximately 3% of rental revenues will be paid to the property manager as a management fee. |
| Counterparty | University of Massachusetts (S&P: AA- / Moody’s: Aa2 / Fitch AA) |
| Contract Expiry | Concession with the University expires after 65 years. |