| Asset Type | Energy and Social Infrastructure |
| Status | Operational |
| Asset Description | 50-year concession to operate and maintain The Ohio State University’s campus district energy system, including the production and/or distribution of steam, chilled water, natural gas, and electricity across the 485-building Columbus campus and implementation of a comprehensive energy conservation program designed to increase system efficiency by 25% or greater. |
| Asset Revenues | In exchange for an upfront payment, the Concessionaire receives three revenue streams: (i) a fixed $45 million per year (escalating at 1.5% per annum); (ii) a return on investment for capital improvements made to the system over the term of the concession; and (iii) payment of operating costs on a pass-through basis. |
| Counterparty | The Ohio State University (S&P: AA; Moody’s: Aa1) |
| Concession Expiry | 2067 |
| Asset Type | Energy Infrastructure |
| Status | Operational |
| Asset Description | 1,415 MW diversified portfolio of 28 wind and solar assets. The portfolio is located in 12 states throughout the US. The projects are prime recontracting and repowering targets, providing significant future opportunity. One of the projects, a 70 MW wind asset in Maryland, will be repowered in 2022-2023. |
| Asset Revenues | The assets are contracted under long-term PPAs with high-grade utility and corporate counterparties that bear a weighted average credit rating of A. |
| Counterparty | Exelon Generation |
| Asset Type | Energy Infrastructure |
| Status | Operational (construction completed in December 2014) |
| Project Description | 101.2 MW wind farm located in the Québec municipalities of Ste-Marguerite-Marie and Causapscal which was developed by Axium Infrastructure under Hydro-Québec’s 2005 call for power. |
| Asset Revenues | 100% of power produced is sold under a 20-year Power Purchase Agreement (PPA) |
| Counterparty | Hydro-Québec |
| PPA expiry | December 2034 (20 years following COD) |
| Asset Type | Transportation infrastructure |
| Status | Operational (COD in October 2007) |
| Asset Description | Design, construction, financing and operation of 11km of new four and six-lane divided roadway forming the southeast quadrant of a larger ring road around the City of Edmonton, as well as maintenance of the existing southwest portion of the highway |
| Counterparty | Province of Alberta |
| Concession Expiry | 2037 (30 years following COD) |
| Asset's Website | For more information visit: www.lafargeinfrastructure.ca/Index.aspx |