| Asset Type | Social infrastructure |
| Status | Operational |
| Project Description | Project involves the design, construction, financing and operation of a 68,500 m2 state-of-the-art clinical research centre facility focused on innovation, non-invasive human exploration and knowledge transfer for health care services and teaching. |
| Asset Revenues | 100% availability-based (no exposure to volume / market risk) |
| Counterparty | CHUM Hospital (payments supported by the province of Québec) |
| Concession Expiry | 2043 |
| Asset Website | For more information, visit: http://crchum.chumontreal.qc.ca/en |
| Asset Type | Energy Infrastructure |
| Status | Operational |
| Asset Description | Quality Wind: a 142.2 MW wind facility located near Tumbler Ridge in northeastern British Columbia PDN Wind: a 104.4 MW wind facility located in Haldimand and Norfolk Counties in southern Ontario |
| Asset Revenues | 100% of the power produced is sold to BC Hydro and the IESO under long-term Power Purchase Agreements (PPA), with a capacity-weighted remaining term of approximately 11 years. |
| Counterparty | BC Hydro and IESO |
| Asset Type | Energy Infrastructure (Transmission Line and Station) |
| Status | Under Final Development (COD expected by end of 2027) |
| Asset Description | 10 km double-circuit 230kV transmission line and 230kV transformer station located within the city of Sault Ste. Marie. Among other connections, this asset will power Algoma Steel Inc. (large Canadian steelmaker)’s transition from using coal to clean electricity (via electric arc furnaces) and reduce its CO2 emissions by 70% (3 million tons annually). |
| Asset Revenues | The asset will be governed under the Ontario regulatory utility framework through which it will be entitled to recover all prudently incurred costs plus a regulated return on its debt and equity through a performance based ratemaking scheme. |
| Counterparty | Settlement counterparty: IESO (rated Aa3 by Moody’s) Regulator: Ontario Energy Board |
| Asset Type | Energy and Social Infrastructure |
| Status | Operational |
| Asset Description | 50-year concession to operate, maintain and upgrade the Georgetown University utility system, which is all of the electric, steam and condensate, natural gas, chilled water and associated central assets serving the Main and Downtown campuses, and includes utility and energy services to the Jesuit Community, the Georgetown University Medical Center and MedStar Georgetown Hospital. The concessionaire will also implement energy conservation measures to achieve a 35% reduction in energy use intensity |
| Asset Revenues | In exchange for an upfront payment, the Concessionaire receives three revenues steams: (i) a starting fixed fee of $21.1 million that grows by ~$2.2 million per year until 2031, then growing at 1.5% per year; (ii) a return on investment for capital improvements made to the system over the term of the concession; and (iii) payment of operating costs on a pass-through basis |
| Counterparty | Georgetown University (S&P: A-; Moody’s: A3) |
| Concession Expiry | 2071 |