| Asset Type | Energy Infrastructure |
| Status | Operational (COD in December 2015) |
| Asset Description | 40 MW operating wind facility located in Dufferin County, Ontario. The wind facility was developed under Ontario’s Feed-in-Tariff (FiT) program. |
| Asset Revenues | 100% of power produced is sold to the IESO under a 20-year Power Purchase Agreement (PPA). |
| Counterparty | IESO (rated Aa3 by Moody’s) |
| Asset Type | Energy and Social Infrastructure |
| Status | Operational |
| Asset Description | 50-year concession to operate, maintain and upgrade the Georgetown University utility system, which is all of the electric, steam and condensate, natural gas, chilled water and associated central assets serving the Main and Downtown campuses, and includes utility and energy services to the Jesuit Community, the Georgetown University Medical Center and MedStar Georgetown Hospital. The concessionaire will also implement energy conservation measures to achieve a 35% reduction in energy use intensity |
| Asset Revenues | In exchange for an upfront payment, the Concessionaire receives three revenues steams: (i) a starting fixed fee of $21.1 million that grows by ~$2.2 million per year until 2031, then growing at 1.5% per year; (ii) a return on investment for capital improvements made to the system over the term of the concession; and (iii) payment of operating costs on a pass-through basis |
| Counterparty | Georgetown University (S&P: A-; Moody’s: A3) |
| Concession Expiry | 2071 |
| Asset Type | Energy Infrastructure |
| Status | Operational (COD in August 2011 for Copper Crossing and November 2010 for Dry Lake II) |
| Asset Description | 50% interest in a portfolio of two operating renewable projects, one 65.1 MW wind farm (Dry Lake II) and one 23 MWdc solar farm (Copper Crossing), both located in Arizona and fully contracted under long- term PPAs. |
| Asset type | Energy Infrastructure |
| Status | Operational (COD in October 2015) |
| Asset Description | 100 MW operating wind facility located in Lambton County, Ontario. The wind facility was developed under Ontario’s Feed-in-Tariff (FiT) program. |
| Asset Revenues | 100% of power produced is sold to the IESO under a 20-year Power Purchase Agreement (PPA). |
| Counterparty | IESO (rated Aa3 by Moody’s) |
No Comments