| Asset Type | Energy Infrastructure |
| Status | Operational (COD in December 2015) |
| Asset Description | 150 MW wind project utilizing Vestas turbine technology, with turbine and Balance of Plant (BOP) operations and maintenance services provided by Vestas and EDF Renewable Services. |
| Asset Revenues | 100% of power produced is sold under a 20 year term Power Purchase Agreement (PPA). |
| Counterparty | Kansas City Power & Light |
| PPA Expiry | 2036 (20 years following COD) |
| Asset Type | Energy Infrastructure (Battery Storage) |
| Status | Operational |
| Asset Description | 350MW (1400MWhs) battery storage project located in southern California. Construction is anticipated to start in August 2021 with COD in August 2022. Once operational, the project will provide capacity and crucial supply-shifting benefits to the California grid. The project has 2 ~15-year offtake contracts for the total project capacity. |
| Asset Revenues | 200MW are contracted under a tolling agreement for 14 years and 10 months, during which there is no merchant exposure. 150MW are contracted under a capacity contract for 15 years, during which it will earn energy arbitrage revenues on a merchant basis. |
| Counterparties | Recurrent Energy, Southern California Edison (SCE), Pacific Gas & Electric (PG&E) |
| Contract Expiry | Project offtake agreements terminate in ~15 years, with the project earning revenue on a merchant basis thereafter. |
| Asset Type | Energy Infrastructure |
| Status | Operational (COD in October 2012) |
| Asset Description | 80 MW wind farm located in the municipality of Saint-Robert-Bellarmin, Québec. The project was developed by EDF EN Canada, and is fully contracted under a 20-year Power Purchase Agreement with Hydro-Québec. |
| Asset Revenues | 100% of power produced is sold under a 20-year Power Purchase Agreement. |
| Counterparty | Hydro-Québec |
| PPA Expiry | 2032 (20 years following COD) |
| Asset Type | Energy Infrastructure |
| Status | Under construction (commercial operations in Q2/Q3 2024) |
| Asset Description | Equity interest in a shovel-ready 900 MW combined-cycle power plant to be located approximately 200 km west of Edmonton, AB. |
| Asset Revenues | Market energy sales with ~80% of the gas supply sourced via three 14 years average gas netback agreements (gas prices indexed to electricity prices). |
| Counterparties | Peyto Exploration & Development Corp. – Pacific Canbriam Energy Ltd. – Cutbank Dawson Gas Resources Ltd. |